This unique 54 hectare site is located in the fast growing region of the Illawarra.

This large lot subdivision takes best advantage of the land form and the view with the potential for approximately 44 Lots between 1,000 and 2,800 sqm and 41 Lots from 5,000 sqm

The tranquil setting and secluded location of this site will provide a coastal lifestyle whilst surrounded by natural bush land. Enjoy your privacy in this beautiful setting while still being close to all the Illawarra has to offer. With Wollongong CBD, Schools, beaches, Wollongong University and various surrounding commercial districts a short drive away, you’ll have all the convenience and facilities you need.

I offer the following information regarding the status update for Cordeaux Heights:

Recent assessments complete by Indesco (and sub-consultants to date):

Flora Fauna Assessment
Bushfire Assessment
Riparian Assessment (realignment/truncation)
Preliminary Civil Design and Costing
Visual Assessment
Geotechnical Advice (rock strength and feasibility of filling gullies)
Servicing Assessment (Sydney Water, Endeavor Energy, NBN, Jemena Gas)

Assessments required for DA lodgement (based on typical DA requirements and pre-lodgement advice 29 July 2019):

Landscape Architecture Design
Aboriginal Due Diligence Assessment
Contamination Preliminary Site Investigation
Geotechnical Assessment
Water Cycle Management Study (WCMS)
Visual Assessment Update
Traffic and Transport Assessment
Statement of Environmental Effects
Engineering Design Documentation for DA Submission

The price is $12,750,000

Development costs $16,331,000

We have now completed our initial scope of work for this site looking at an alternative and more viable subdivision approach for the site.

The associated indicative costings are summarised in the table below:

General $230,000.00

Bulk Earthworks $3,540,330.00

Sewer $392,730.00

Stormwater $779,954.00

Roadworks $1,823,935.00

On Site Stormwater Detention Basins and Water Quality $351,650.00

Sediment Erosion Control $80,000.00

Potable water $754,260.00

Electrical $798,500.00

Gas $10,000.00

NBN $94,600.00

Landscaping $337,500.00

Major Culvert $300,000.00

Realignment of Stream $720,000.00

Retaining Walls $2,272,000.00

Contingency (20%) $2,497,091.80

S94A Contributions $149,825.51

Professional Fees (10%) $1,498,255.08

Total Development Cost $16,330,631.39

Total Construction Cost/Lot $189,891.06

With reference to the documentation and costings, I offer the following additional information:

Construction costs are based on indicative bill of quantities obtained from the provided preliminary design documentation which includes conceptual bulk earthworks surface, road design, stormwater design, and sewer/potable water design.
The earthworks surface has resulted in a net fill shortage (import requirement) of approximately 116,000 m3. We have assumed that this fill shortage will be addressed with coal wash and that it will be delivered to site at no cost. This is based on our experience with fill dependant developments in the region.
All rates included in the assessment are based on recent tender rates received in the Illawarra from projects of similar magnitude and scope.
Rock strength and associated costs for rock earthworks are based on a preliminary assessment of the geotechnical information provided in the Expression of Interest (Douglas Partners report).
WCC S94 plan indicates that the development is liable for S94A contributions (1% of the construction costs) with no Special Infrastructure Contributions (SIC) applicable.
Potable water connections exist at the end of both Staff Road and Callistemon Road and our costings are based on extending these lines to service the development. We have also included a fee for a small booster pump and for the relocation of the 300mm water main required to support the earthworks for Road 02 and associated building envelope for Lot 50.
The existing sewer at Staff Road and Callistemon Road can accommodate the equivalent population for the E4 zoned land.
On-site sewerage management systems will be utilised for E3 zoned land based on WCC’s DCP – Chapter E8 (aerated wastewater treatment system).
No significant lead-ins or backhauls have been allowed for the electrical, NBN, and gas.

I would recommend a site ins…